Bondi Road Outfall Drain
Bondi Road Outfall Drain
Bonbeach, Vic
Project Duration >
June 2024 to March 2025
Client >
Kingston City Council
Project Value >
$ 4.1m
Jaydo was engaged to construct a stormwater outfall and rising main to connect with the existing council infrastructure. The project saw the delivery of 1350 dia stormwater pipe layed through a street scape and oval towards the wetlands, along with two custom pit structures, tunnel boring underneath AC sewer lines and the connection of the rising main into the existing pump station.
key challenges
- Being below the water table there was excessive amounts of ground water to be dealt with whilst delivering the pipe lay
- Dealing with acid sulphate material needed constant consideration with duration allowed on site, correct handling, and disposal
- Existing services and poor ground conditions throughout the area of works
- Access constraints and pedestrian traffic
key innovations
- An aggy line was placed underneath the pipeline to dewater and lower the ground water table, stopping the excessive amounts of ground water
- Effective disposal methods for the acid sulphate