Balmain Estate Stages 2A, 3, 4, 5, 6, 7, 8
Balmain Estate Stages 2A, 3, 4, 5, 6, 7, 8
Donnybrook, Vic
Project Duration >
July 2025 to March 2026
Client >
Lojac
Project Value >
$ 2.1m
Construction of stormwater pipes and pits in an urban estate. The Balmain Estate development consisted of multiple stages that will drain into a large outfall.
key challenges
- The terrain of this project was majority hard rock, causing excessive hammering with the excavators. Being a large job with lots of contractors hammering rock meant the pipelaying staging and lines ready to be laid was compartmentalised needing experienced pipelayers to ensure levels were perfect.
key innovations
- To prevent stopping any works, the Jaydo crew worked alongside the client to best utilise the truck movements in and out of site.
value for money
- Pre-trenching long lines with an additional operator saved time and money with crew costs.