Balmain Estate Stages 2A, 3, 4, 5, 6, 7, 8

Balmain Estate Stages 2A, 3, 4, 5, 6, 7, 8

Donnybrook, Vic

Project Duration

July 2025 to March 2026

Client

Lojac

Project Value

$ 2.1m

Construction of stormwater pipes and pits in an urban estate. The Balmain Estate development consisted of multiple stages that will drain into a large outfall.

key challenges

  • The terrain of this project was majority hard rock, causing excessive hammering with the excavators. Being a large job with lots of contractors hammering rock meant the pipelaying staging and lines ready to be laid was compartmentalised needing experienced pipelayers to ensure levels were perfect.

key innovations

  • To prevent stopping any works, the Jaydo crew worked alongside the client to best utilise the truck movements in and out of site.

value for money

  • Pre-trenching long lines with an additional operator saved time and money with crew costs.