Project Duration

April to July 2025

Client

Coliban Water

Project Value

$ 527k

The first project delivered as part of Coliban Water’s Sewer and Water Network Upgrades panel, the works included construction of a new sewer pump station and odour control unit.

key challenges

  • Being new to the area and working with Coliban Water for the first time, the Jaydo team prioritised building strong relationships with local subcontractors and suppliers

key innovations

  • A nearby landowner enabled surplus fill from the construction to be reused

value for money

Multiple aspects of the program were successfully completed at the same time due to an experienced crew, which allowed for cost savings on labour.