Pascoe Vale Rd Water Main Renewal

Pascoe Vale Rd Water Main Renewal

Melbourne, Vic

Project Duration

January 2022 to September 2024

Client

Greater Western Water

Project Value

$ 6.8m

Jaydo was engaged by GWW for the design and construct project to replace three aging water mains within Pascoe Vale Road in Melbourne’s western suburbs.

  • Installation of 1.4km of 502mm MSCL transfer main
  • 1.1km of 280mm PE main
  • 300m slip lined 180mm retic water mains
  • 90+ property connections and 20+ retic/branch connections
  • Decommission 1km of 375 CI main, 300 CI main and 100 CI mains within Pascoe Vale Rd

key challenges

  • Construction of large 502mm main within small works corridor in heavily built-up residential area
  • Construction within Pascoe Vale Road, highly trafficked road with tram tracks and significant commercial/residential considerations
  • Works within restricted traffic times for both road and tram traffic
  • Excavation within areas of abundant existing and redundant services/assets

key innovations & outcomes

  • Rolling road closures – works were completed one block at a time to minimise road closure impacts in the area
  • Mixture of day and night works
  • Construction methodology changes – used trenchless installation for the new alignment for retic mains, which meant no temporary supplies were required
  • Consultation manager was used so the project had full time stakeholder engagement