Parkwood Terrace Reserve Desilting Works

Parkwood Terrace Reserve Desilting Works

Point Cook, Vic

Project Duration

May to July 2025

Client

Wyndham City Council

Project Value

$ 361k

Jaydo was engaged for the desilting of Parkwood Terrace Reserve Wetland to restore it to it’s original water-holding capacity, enhance stormwater treatment performance, and support it’s overall ecological health.

The scope of works included vegetation management, rock beaching, improvements to access pathways, and site reinstatement, with all works carried out in accordance with Environmental Management Plans and EPA guidelines.

key challenges

  • Safeguarding trees, footpaths, and park irrigation systems
  • Managing access and use of parkland with heavy vehicles and machinery while avoiding damage
  • Minimising disruption to nearby residents in this residential park setting
  • Conducting silt removal and rock beaching works in a wetland area during wetter months and following significant rain events

value for money

  • Jaydo was able to  source specialised rock beaching materials, often limited in availability from standard suppliers
  • Coordinated deliveries independently and efficiently
  • Jaydo’s experienced in-house crew skilled in rock beaching installation provided efficiency to the program of works