Hallam Valley Wetlands Reset

Hallam Valley Wetlands Reset

Dandenong South, Vic

Project Duration

October 2023 to May 2024

Client

Melbourne Water

Project Value

$ 1.4m

Jaydo was engaged by Melbourne Water to enhance the bathymetry of the existing Hallam Valley wetlands. The project involved constructing 2,000 tonnes of rock-lined channels and undertaking 3,500m³ of earthworks for regrading. Excavated material, which was contaminated with alligator weed, was managed and buried on-site in accordance with Agriculture Victoria permit conditions.

key challenges

  • Frequent flooding of the wetland site posed a significant challenge. Due to the existing wetland schematics, diverting upstream water flows was not feasible. To manage this, Jaydo deployed a bypass system comprising 2 x 200mm, 4 x 150mm, and 2 x 75mm diesel pumps to redirect incoming
    flows.

key innovations

  • Low ground pressure earthmoving equipment was used to minimise disturbance to existing ground conditions.
  • Strategic schematic planning reduced the site’s exposure to flooding.
  • Multiple work crews operated concurrently, helping to shorten the overall project duration and mitigate flood-related risks.

value for money

  • Jaydo delivered a complete turnkey solution with minimal need for client oversight.
  • All construction activities were undertaken in-house, ensuring efficiency and cost effectiveness.